Package No. 39, Nam Dinh 1 – Thanh Hoa section of the 500kV circuit 3 line project has completed the pole erection and wire pulling work, exceeding the schedule set by the investor.
To achieve this result, right from the first days of implementation, the unit proactively built construction roads to facilitate the transportation of materials to the construction site, significantly shortening construction time compared to having to Perform manual transport.
Mr. Hao’s family has more than 1,400 square meters of rice land, most of which is in the corridor of the 500kV circuit 3 line project.
Understanding the role and meaning of the 500kV circuit 3 line, as soon as the government issues According to his family’s policy, households in the commune soon handed over arable land to implement the project.
“Every part of the land is supported by the people. It’s not that we have to pay money to give up the land, but we let the construction work first, people get the money later,” Mr. Mai Van Hao – Nga Giap commune, Nga district Son, Thanh Hoa province shared.
Package No. 39 has a total length of 6km with 18 column foundation positions.
Construction of column erection and wire pulling was completed on June 8.
In Nga Giap commune, the area of land recovered to implement this bidding package is more than 1 hectare, and after exactly 1 month of implementation, 100% of the project’s site was handed over to the investor.
Mr. Nguyen Van Dung – Chairman of the People’s Committee of Nga Giap commune, Nga Son district, Thanh Hoa province said: “Aware that this is a key national project, all of us Nga Giap people are very responsive and create everything possible.”
In order for the project to be completed, up to now we have handed over to the project 100% of the acquired area, including the area affected by the project corridor.”
Immediately after the site clearance work was completed, taking advantage of favorable weather, the construction work was immediately implemented by the contractor.
Especially during the days last week, despite the harsh weather, all construction teams on the construction site deployed 3 shifts and 4 crews in accordance with the guiding spirit of the project.
“During the process of erecting the pole and pulling the rope to reach the finish line, ensuring fast progress, until today it was completed, the contractor received a lot of support from the people, especially the local government.
to route the corridor, to ensure that the wire pulling work is not postponed for any day,” said Mr. Le The Hanh – Director of Phuong Hanh Co., Ltd.
Mr. Luu Viet Tien – Deputy General Director of the National Power Transmission Corporation said: “We are trying to implement the remaining tasks to reach technical basis by June 20 and complete the entire project.”
on June 30 under the direction of the Prime Minister.”
As of the end of yesterday, on the entire route of the 500kV circuit 3 line project from Quang Trach, Quang Binh province to Pho Noi, Hung Yen province, localities have handed over 494/513 corridor corridors.
Regarding construction progress, 581 steel columns have been installed and 398 steel columns are under construction; Completed pulling the rope for 43 intervals, pulling the rope for 39 intervals.
News
Van Ban Electricity: Ensuring effective exploitation of the distance meter system
As we approach the end of May 2024, Van Ban Electricity has made significant strides in modernizing its electricity management system. With a customer base of 26,135, the company has successfully implemented a long-distance electronic meter system, ensuring accurate and…
Good news for Vietnamese rice
The recent announcement by Mr. Arsenio Balisacan, Minister of Economy and National Development of the Philippines, regarding the reduction of import tax on rice has significant implications for both the Philippines and its trading partners, particularly Vietnam. This decision to…
A joint venture of 3 contractors won the bid for the new construction project of Bac Ha district administrative center
The Bac Ha District Construction Investment Project Management Board has recently announced the selection of the contractor for package No. 5 to construct works under the Bac Ha District Administrative Center Headquarters project. The new administrative center of Bac Ha…
The Nhon – Hanoi railway line is eligible to operate at the end of June
As planned, 10 trains of the pilot urban railway line in Hanoi, Nhon – Hanoi station section have just been granted a Certificate of quality, technical safety and environmental protection by the Vietnam Register. railway transport. Illustration photo: Trung Nguyen/News…
Promote investment promotion in the agricultural sector
On the morning of June 6, the Provincial Department of Agriculture and Rural Development organized a conference to promote investment in the agricultural sector in Lao Cai province. Conference scene. The conference was attended by leaders of the Department of…
Sa Pa has basically completed seasonal rice cultivation
Sa Pa town in Vietnam has laid out an ambitious plan for this year’s rice crop, aiming to cultivate 3,600 hectares with a variety of rice types. The town’s agricultural sector is taking advantage of favorable weather and abundant water…
End of content
No more pages to load