Gói thầu đầu tiên dự án 500KV mạch 3 hoàn thành thi công | VTV.VN


Package No. 39, Nam Dinh 1 – Thanh Hoa section of the 500kV circuit 3 line project has completed the pole erection and wire pulling work, exceeding the schedule set by the investor.

To achieve this result, right from the first days of implementation, the unit proactively built construction roads to facilitate the transportation of materials to the construction site, significantly shortening construction time compared to having to Perform manual transport.

Along with that, the support of the people and authorities in Nga Son district, Thanh Hoa province also contributes to ensuring the goal of completing the entire project earlier than planned.

Mr. Hao’s family has more than 1,400 square meters of rice land, most of which is in the corridor of the 500kV circuit 3 line project.

Understanding the role and meaning of the 500kV circuit 3 line, as soon as the government issues According to his family’s policy, households in the commune soon handed over arable land to implement the project.

“Every part of the land is supported by the people. It’s not that we have to pay money to give up the land, but we let the construction work first, people get the money later,” Mr. Mai Van Hao – Nga Giap commune, Nga district Son, Thanh Hoa province shared.

Package No. 39 has a total length of 6km with 18 column foundation positions.

Sốt ruột tiến độ đường dây 500kV mạch 3, Thủ tướng 'truy' từng vướng mắc để  tháo gỡ - Tuổi Trẻ Online

Construction of column erection and wire pulling was completed on June 8.

In Nga Giap commune, the area of ​​land recovered to implement this bidding package is more than 1 hectare, and after exactly 1 month of implementation, 100% of the project’s site was handed over to the investor.

Mr. Nguyen Van Dung – Chairman of the People’s Committee of Nga Giap commune, Nga Son district, Thanh Hoa province said: “Aware that this is a key national project, all of us Nga Giap people are very responsive and create everything possible.”

In order for the project to be completed, up to now we have handed over to the project 100% of the acquired area, including the area affected by the project corridor.”

Immediately after the site clearance work was completed, taking advantage of favorable weather, the construction work was immediately implemented by the contractor.

Especially during the days last week, despite the harsh weather, all construction teams on the construction site deployed 3 shifts and 4 crews in accordance with the guiding spirit of the project.

“During the process of erecting the pole and pulling the rope to reach the finish line, ensuring fast progress, until today it was completed, the contractor received a lot of support from the people, especially the local government.

to route the corridor, to ensure that the wire pulling work is not postponed for any day,” said Mr. Le The Hanh – Director of Phuong Hanh Co., Ltd.

Mr. Luu Viet Tien – Deputy General Director of the National Power Transmission Corporation said: “We are trying to implement the remaining tasks to reach technical basis by June 20 and complete the entire project.”

on June 30 under the direction of the Prime Minister.”

As of the end of yesterday, on the entire route of the 500kV circuit 3 line project from Quang Trach, Quang Binh province to Pho Noi, Hung Yen province, localities have handed over 494/513 corridor corridors.

Regarding construction progress, 581 steel columns have been installed and 398 steel columns are under construction; Completed pulling the rope for 43 intervals, pulling the rope for 39 intervals.